Seismic Safety & Modernization new facility
CURRENT STATUS: April 2024
Installation of underground electrical duct-banks is in progress.
Installation of storm drain and sanitary sewer lines is in progress.
Installation of underground electrical at Building 70A loading dock is in progress.
Demolition of retaining wall at Building 70A loading dock completed in early April.
Drilling of soldier piles for soil retaining system will be completed in April.
Mass soil excavation will be completed in April.
Waterproofing and shotcrete of retaining walls will commenced in March.
Heavy construction traffic with impacts to parking near Bldgs. 50, 70, and 70A from mid March through June. See Construction Impacts website for details.
QUICK LINKS
Receive email updates on this project
PROJECT CONTACTS
All project questions: SSM_THUP@lbl.gov
Project Director: Lisa Ehlers
Project Manager: Marc Restrepo
Construction Manager: Lindsay Nakaki
EXPECTED IMPACTS
Traffic
During certain phases of the project construction truck traffic and lane closures on Chu Road, Smoot Road, and Lawrence Road will impact vehicle traffic and shuttle schedules.
Large or wide trucks or equipment will cause delays at Blackberry Gate. Notifications will be sent directing traffic to use Strawberry Gate as needed.
There will be increased construction equipment and personnel along Lawrence Road from February 2023 through 2026.
Details, including mitigation efforts, once confirmed will be posted to this page and shared via email and Elements.
B70/70A Loading Dock Area
The fenced construction work zone impacts the B70/70A loading dock area.
The area is fenced from the bottled gas storage area to the B70A access ramp.
Loading dock access and gas deliveries will be maintained.
The existing argon tank has been relocated.
Nitrogen lines to B70A have been rerouted.
Food Services
Food trucks are offering coffee, breakfast, and lunch outside Building 91.
Refer to food.lbl.gov for food service information and updates.
Access Restrictions and Pedestrian Paths
The construction area, including the entire K1 parking lot, has been enclosed by fencing and is now restricted to construction personnel only.
Our primary goal in putting up the fence is to keep everyone safe.
We know it is frustrating to take a longer path between buildings. For your safety, however, it is important to remain outside the fence perimeter.
Construction project work areas include inherent hazards related to the nature of construction work (e.g. moving equipment, open trenches, potential soft or uneven terrain, tripping hazards, etc.). The fence location will shield pedestrians from construction activities and potentially dangerous equipment.
The fence cuts off previously used pedestrian pathways between the buildings above Lawrence Road (ALS, Guest House, etc.) and the buildings below the construction site (50 complex, 70 complex, etc.). There is pedestrian access along Lawrence Road, around the J Lot, and along Smoot Road.
Parking
Parking lot K1 (cafeteria parking lot) is closed and fenced off for the duration of construction.
Shuttle Service
The downhill shuttle stop at Building 54 closed on February 1, 2023, and a new downhill stop opened the same day in front of Building 23 (Guest House).
Noise, Vibrations, and Dust
The construction activities will be disruptive. Noise and minimal vibrations from heavy construction equipment are expected and will be closely coordinated with neighboring buildings. EH&S is continually monitoring noise and dust levels.
The construction teams plan to use methods similar to those successfully used during BioEPIC's construction to mitigate vibrations as much as possible.
PIMD will convene periodic coordination meetings throughout construction to keep science partners informed of the overall schedule as well as more aggressive activities (e.g., hydraulic hammer operation during demolition).
Library
If you need consultation or help tracking down books and no one is available in the Library office, 50-4032, please email library@lbl.gov.
SCHEDULE
The schedule is subject to change without notice.
Phase 2 electrical outage is being planned for Fall 2024. See Outages website for updates.
September 2023 to June 2024: Terrace hillside and install slope stabilization shoring walls.
January 2024 to Fall 2026: Construct new facility.
October 2024 to January 2025: Structural steel installation.
AUGUST 28, 2023 ELEMENTS ARTICLE
End of an Era: Cafeteria Building Comes Down
It’s the end of an era for Berkeley Lab. Demolition of Building 54 – which served as the Lab’s cafeteria, among other things, for more than 70 years – began on August 23, 2023. While it will take several weeks to remove all traces, the iconic main story was torn down by the end of the day.
This article contains a selection of images from the Lab archives showing the many activities hosted in Building 54 over the years, as well as renderings of what the future holds for the site, and time-lapse video of the superstructure demolition.
OCTOBER 20, 2022 TOWN HALL
The project team hosted a town hall for the Lab community on October 20. Click the links below to view the recording and the presentation deck.
OVERVIEW
The Seismic Safety & Modernization (SSM) new facility proposal is a multi-year planning and construction effort intended to address seismic safety issues and emergency response capabilities specifically related to Building 54, which currently houses the cafeteria.
As proposed, a new 47,743-square-foot building would consolidate dining, health services, and conference space. The result would be a more operationally efficient campus for Lab employees, visitors, and guests.
The project will demolish Building 54 (Cafeteria), vacate Building 26 (EH&S), and create one building to be situated on the current Building 54 site.
Transit Hub and Utilities Project (THUP)
The Transit Hub and Utilities Project (THUP) is scheduled to take place in tandem with SSM. THUP's scope includes the installation and relocation of several utilities in preparation for SSM.
Lab Updates
The Lab community will receive regular updates on the work and impacts via this page, Elements articles, and select town halls.
Click this link if you want to be added to a list to receive regular email updates.